17th September 2010
| Petition No |
Hearing in the Matter of: |
Date |
| 11/2010 |
Establishment of Comsumer Grievance Redressal Forums.
Compliance of order dated 9.10.2009 of the Hon'ble Appellate Tribunal for Electricity.
And
Electricity Department Goa, Electricity Department Andaman & Nicobar Islands, Electricity Department Chandigarh, Electricity Department Daman & Diu, Electricity Department, Dadra & Nagar Haveli, Electricity Department Lakshdweep, Electricity Department Puducherry. :Respondents
|
17th September 2010 | 12th July 2010
| Petition No |
Hearing in the Matter of: |
Date |
| 11/2010 |
Establishment of Comsumer Grievance Redressal Forums.
Compliance of order dated 9.10.2009 of the Hon'ble Appellate Tribunal for Electricity.
And
Electricity Department Goa, Electricity Department Andaman & Nicobar Islands, Electricity Department Chandigarh, Electricity Department Daman & Diu, Electricity Department, Dadra & Nagar Haveli, Electricity Department Lakshdweep, Electricity Department Puducherry. :Respondents
|
12th July 2010 | 12th July 2010
| Petition No. |
Hearing in the Matter of: |
Date |
| 12/2010 |
Petition in respect of illegal disconnection of their installation HTC-44 Goa in violation of Section 56 (1) (b) of Electricity Act 2003.
1. M/S Sardessai Engineering Works Naguesh Bhavan, Madant, Cortalim Goa, Pin Code No. 403710 Consumer No. HTC-44
2. Shri Prakash B. Sardessai Partner of Complainant No. 1 Naguesh Bhavan, Madant, Cortalim Goa. :Applicants/Complainants
VS
Electricity Department Goa, Through Secretary, Power, Government of Goa, Secretariat, Porvorim, Goa :Respondent
|
12th July 2010 | 12th July 2010
| Petition No |
Hearing in the Matter of: |
Date |
| 7/2009-Misc |
Petition under section 86(1) (f) of the electricity act 2003; for direction to the respondent to pay the long standing dues/ for settlement of long pending issues/ payments.
M/s. Suryachakra Power Corporation Limited : Petitioner Plot No. 115, Road No.-54, Jubilee Hills, Hyderabad-500033 Vs
- The Chief Secretary, : Respondents No. 1
Andaman & Nicobar Administration Secretariat, Port Blair Port Blair, Andaman & Nicobar Islands
- Superintending Engineer, : Respondents No. 2
Electricity Department Port Blair, Andaman & Nicobar Islands
|
12th July 2010 | 15th June 2010
| Petition No. |
Hearing in the Matter of: |
Date |
| 12/2010 |
Petition in respect of illegal disconnection of their installation HTC-44 Goa in violation of Section 56 (1) (b) of Electricity Act 2003.
1. M/S Sardessai Engineering Works Naguesh Bhavan, Madant, Cortalim Goa, Pin Code No. 403710 Consumer No. HTC-44
2. Shri Prakash B. Sardessai Partner of Complainant No. 1 Naguesh Bhavan, Madant, Cortalim Goa. :Applicants/Complainants
VS
Electricity Department Goa, Through Secretary, Power, Government of Goa, Secretariat, Porvorim, Goa :Respondent
|
15th June 2010 |
14th June 2010
| Petition No |
Hearing in the Matter of: |
Date |
| 7/2009-Misc |
Petition under section 86(1) (f) of the electricity act 2003; for direction to the respondent to pay the long standing dues/ for settlement of long pending issues/ payments.
M/s. Suryachakra Power Corporation Limited : Petitioner Plot No. 115, Road No.-54, Jubilee Hills, Hyderabad-500033 Vs
- The Chief Secretary, : Respondents No. 1
Andaman & Nicobar Administration Secretariat, Port Blair Port Blair, Andaman & Nicobar Islands
- Superintending Engineer, : Respondents No. 2
Electricity Department Port Blair, Andaman & Nicobar Islands
|
14th June 2010 |
| 13/2010 |
Filing of Aggregate Revenue Requirement (ARR) for the FY 10-11 under Section 62 and 86 of the Electricity Act, 2003
Executive Engineer, Electricity Department of Daman & Diu, Daman :Petitioner |
14th June 2010 |
| 14/2010 |
Filing of Aggregate Revenue Requirement (ARR) and Tariff Proposal for the FY 10-11 under Section 61, 62 and 64 of the Electricity Act, 2003
Superintending Engineer, Electricity Department of Dadar and Nagar Haveli, :Petitioner |
14th June 2010 |
10th June 2010
| Petition No |
Hearing in the Matter of: |
Date |
| 11/2010 |
Establishment of Comsumer Grievance Redressal Forums.
Compliance of order dated 9.10.2009 of the Hon'ble Appellate Tribunal for Electricity.
And
Electricity Department Goa, Electricity Department Andaman & Nicobar Islands, Electricity Department Chandigarh, Electricity Department Daman & Diu, Electricity Department, Dadra & Nagar Haveli, Electricity Department Lakshdweep, Electricity Department Puducherry. :Respondents
|
10th June 2010 |
7th June 2010
| Petition No |
Hearing in the Matter of: |
Date |
| 7/2009-Misc |
Petition under section 86(1) (f) of the electricity act 2003; for direction to the respondent to pay the long standing dues/ for settlement of long pending issues/ payments.
M/s. Suryachakra Power Corporation Limited : Petitioner Plot No. 115, Road No.-54, Jubilee Hills, Hyderabad-500033 Vs
- The Chief Secretary, : Respondents No. 1
Andaman & Nicobar Administration Secretariat, Port Blair Port Blair, Andaman & Nicobar Islands
- Superintending Engineer, : Respondents No. 2
Electricity Department Port Blair, Andaman & Nicobar Islands
|
7th June 2010 |
14th May 2010
| Petition No. |
Hearing in the Matter of: |
Date |
| 12/2010 |
Petition in respect of illegal disconnection of their installation HTC-44 Goa in violation of Section 56 (1) (b) of Electricity Act 2003.
1. M/S Sardessai Engineering Works Naguesh Bhavan, Madant, Cortalim Goa, Pin Code No. 403710 Consumer No. HTC-44
2. Shri Prakash B. Sardessai Partner of Complainant No. 1 Naguesh Bhavan, Madant, Cortalim Goa. :Applicants/Complainants
VS
Electricity Department Goa, Through Secretary, Power, Government of Goa, Secretariat, Porvorim, Goa :Respondent
|
14th May 2010 |
| 13/2010 |
Filing of Aggregate Revenue Requirement (ARR) for the FY 10-11 under Section 62 and 86 of the Electricity Act, 2003
Executive Engineer, Electricity Department of Daman & Diu, Daman :Petitioner |
14th May 2010 |
23rd March 2010
| Petition No |
Hearing in the Matter of: |
Date |
| 7/2009-Misc |
Petition under section 86(1) (f) of the electricity act 2003; for direction to the respondent to pay the long standing dues/ for settlement of long pending issues/ payments.
M/s. Suryachakra Power Corporation Limited : Petitioner Plot No. 115, Road No.-54, Jubilee Hills, Hyderabad-500033 Vs
- The Chief Secretary, : Respondents No. 1
Andaman & Nicobar Administration Secretariat, Port Blair Port Blair, Andaman & Nicobar Islands
- Superintending Engineer, : Respondents No. 2
Electricity Department Port Blair, Andaman & Nicobar Islands
|
23rd March 2010 |
23rd February 2010
| Petition No |
Hearing in the Matter of: |
Date |
| 7/2009-Misc |
Petition under section 86(1) (f) of the electricity act 2003; for direction to the respondent to pay the long standing dues/ for settlement of long pending issues/ payments.
M/s. Suryachakra Power Corporation Limited : Petitioner Plot No. 115, Road No.-54, Jubilee Hills, Hyderabad-500033 Vs
- The Chief Secretary, : Respondents No. 1
Andaman & Nicobar Administration Secretariat, Port Blair Port Blair, Andaman & Nicobar Islands
- Superintending Engineer, : Respondents No. 2
Electricity Department Port Blair, Andaman & Nicobar Islands
|
23rd February 2010 |
28th January 2010
| Petition No |
Hearing in the Matter of: |
Date |
| 7/2009-Misc |
Petition under section 86(1) (f) of the electricity act 2003; for direction to the respondent to pay the long standing dues/ for settlement of long pending issues/ payments.
M/s. Suryachakra Power Corporation Limited : Petitioner Plot No. 115, Road No.-54, Jubilee Hills, Hyderabad-500033 Vs
- The Chief Secretary, : Respondents No. 1
Andaman & Nicobar Administration Secretariat, Port Blair Port Blair, Andaman & Nicobar Islands
- Superintending Engineer, : Respondents No. 2
Electricity Department Port Blair, Andaman & Nicobar Islands
|
28th January 2010 |
25th January 2010
| Petition No |
Hearing in the Matter of: |
Date |
| 1/2009-Misc |
Approval of filing of Annual Revenue Requirement (ARR) for the financial year 2009-10 for determination of Tariff (for distribution and retail sale of Electricity) of Electricity Department Puducherry.
|
25th January 2010 | 6th January 2010
| Petition No |
Hearing in the Matter of: |
Date |
| 7/2009-Misc |
Petition under section 86(1) (f) of the electricity act 2003; for direction to the respondent to pay the long standing dues/ for settlement of long pending issues/ payments.
M/s. Suryachakra Power Corporation Limited : Petitioner Plot No. 115, Road No.-54, Jubilee Hills, Hyderabad-500033 Vs
- The Chief Secretary, : Respondents No. 1
Andaman & Nicobar Administration Secretariat, Port Blair Port Blair, Andaman & Nicobar Islands
- Superintending Engineer, : Respondents No. 2
Electricity Department Port Blair, Andaman & Nicobar Islands
|
6th January 2010 |
5th January 2010
| Petition No |
Hearing in the Matter of: |
Date |
| 9/2009-Misc |
Issuing No Objection Certificates (NOC) / permission for use of short term open access for wheeling of power.
M/s. HINDALCO Industries Ltd.; Village - khutli, Khanvel P. O. Silvassa - 396 230 (UT of Daman & Nagar Haveli), Regd. Office: Century Bhavan, 3rd floor, Dr. Annie Besant Road, Mumbai # 400030 : PETITIONERS Vs
- The Electricity Department of Dadra & Nagar Haveli,
Through its Superintendent Engineer, Opposite secretariate building, Amli Road, Union Territory of Dadra & Nagar Haveli
- The Executive Engineer,
Electricity Department of Dadra & Nagar Haveli, Opposite Secretariate building, Port Blair, Andaman & Nicobar Islands : RESPONDENTS
|
5th January 2010 |
5th January 2010
| Petition No |
Hearing in the Matter of: |
Date |
| 8/2009-Misc |
Issuing No Objection Certificates (NOC)/ permission for use of short term open access for wheeling / purchase of power.
Sterlite Industries (I) Ltd.; : Petitioner Cooper Division, 1/1/2, Chinchpada, Slivassa, 396 230. Dadra & Nagar Haveli, (U.T.); India Redg. Office: SIPCOT, Industrial Complex, Madhurai Bypass Road, T.V. Puram; India Tuticorin, 628 002, Tamilnadu; India.
V/S
- The Electricity Department of Dadra & Nagar Haveli, : Respondents No. 1
Through its Superintendent Engineer, Opposite Secretariat building, Amli Road, Union Territory of Dadra & Nagar Haveli
- The Executive Engineer, : Respondents No. 2
Electricity Department of Dadra & Nagar Haveli, Opposite Secretariat building, Amli Road, Union Territory of Dadra & Nagar Haveli |
5th January 2010 |
9th December 2009
| Sl No |
Hearing in the Matter of: |
Date |
| 1 |
Petition under section 86(1) (f) of the electricity act 2003; for direction to the respondent to pay the long standing dues/ for settlement of long pending issues/ payments.
M/s. Suryachakra Power Corporation Limited : Petitioner Plot No. 115, Road No.-54, Jubilee Hills, Hyderabad-500033 Vs
- The Chief Secretary, : Respondents No. 1
Andaman & Nicobar Administration Secretariat, Port Blair Port Blair, Andaman & Nicobar Islands
- Superintending Engineer, : Respondents No. 2
Electricity Department Port Blair, Andaman & Nicobar Islands
|
9th December 2009 |
| 2 |
Issuing No Objection Certificates (NOC)/ permission for use of short term open access for wheeling / purchase of power.
Sterlite Industries (I) Ltd.; : Petitioner Cooper Division, 1/1/2, Chinchpada, Slivassa, 396 230. Dadra & Nagar Haveli, (U.T.); India Redg. Office: SIPCOT, Industrial Complex, Madhurai Bypass Road, T.V. Puram; India Tuticorin, 628 002, Tamilnadu; India.
V/S
- The Electricity Department of Dadra & Nagar Haveli, : Respondents No. 1
Through its Superintendent Engineer, Opposite Secretariat building, Amli Road, Union Territory of Dadra & Nagar Haveli
- The Executive Engineer, : Respondents No. 2
Electricity Department of Dadra & Nagar Haveli, Opposite Secretariat building, Amli Road, Union Territory of Dadra & Nagar Haveli |
9th December 2009 |
Yet to be fixed
| Sl No |
Hearing in the Matter of: |
Date |
| 1 |
Deferral of Public Hearing on Aggregate Revenue Requirement (ARR) and determination of Tariff for Retail sale of Electricity for the FY 2009-10 filed by Electricity Department, Puducherry (EDP) |
Yet to be fixed. |
25th September 2009
| Sl No |
Hearing in the Matter of: |
Date |
| 1 |
Open Access of power for Consumers in Union Territory of Dadra and Nagar Haveli |
25th September 2009 |
| 2 |
Determination/Revision of tariff for funance based and rolling mill based consumers of the UT Dadra and Nagar Haveli.
Steel Industries Association: Petitioner Dadra and Nagar Haveli, UT V/S Administration of UT Dadra and Nagar : Respondents. Heveli and Others |
25th September 2009 |
| 3 |
Wheeling or Purchase of power from other sources including Captive power plant of sister concern situated outside union territories. |
25th September 2009 |
3rd September 2009
| Sl No |
Hearing in the Matter of: |
Date |
| 1 |
Hearing for Initiation of Competitive Bidding Process for procurement of 100 MW Power for short term under Competitive Bidding. |
3rd September 2009 |
| 2 |
Hearing for admission of the petition in the matter of M/S Surya Chapra Power Corporation Limited V/S Supritending Engineer, Electricity Department, Port Blair. |
3rd September 2009 |
| 3 |
Hearing of admission of the Petition in the matter of Approval of Filing of Aggregate Revenue Requirement (ARR) for financial year 2009-10 for determination of Tariff (for Distribution and Retail Sale of Electricity) Electricity Department, Puducherry. |
3rd September 2009 |
| 4 |
Hearing for admission of the Petition in the matter of Setting up 2 x 10 MW Renewable Energy (Biomass) Power Projects in Andaman and Nicobar Islands by Surya Chakra Power Corporation Ltd - fixing up to Tariff- Reg. |
3rd September 2009 |
|
|
|
|
|
|
|